Jointing Sand Calculator
Calculate how much bedding sand and kiln-dried jointing sand you need for block paving in Gibraltar. Get volume, weight and cost.
How Much Paver Sand Do You Need?
Paver sand covers two different jobs on the same project: a bedding layer the pavers are laid and levelled on, and joint sand that fills the gaps between them once they're set. Getting either quantity wrong usually means a mid-job supply run. This calculator works out both volumes -- plus the combined weight, bag count, and cost -- from your paved area, bedding depth, chosen sand type, and an optional joint-fill calculation.
How to Use the Paver Sand Calculator
- Enter the length and width of the area you're paving.
- Enter the bedding depth -- typically 2.5 cm (1 in) compacted -- and pick a sand type: sharp/bedding sand, polymeric jointing sand, or stone dust (limestone screenings).
- Turn on joint fill if you need a separate joint-sand quantity, and enter the joint depth (roughly your paver's thickness) -- the calculator adds that volume to the bedding layer and returns total volume, weight, bag count, and estimated cost.
The Paver Sand Formula
Bedding volume = Area x bedding depth. When joint fill is included, joint volume = Area x joint-area fraction (the share of the paved surface that's open joint, typically 3-5%) x joint depth. The two volumes are added, a waste allowance applied, then multiplied by the sand's bulk density to get weight.
Worked example: a 5 m x 4 m patio (20 m²), 2.5 cm (0.025 m) bedding depth, sharp sand at 1,600 kg/m³, plus joint fill at a 4% joint-area fraction and 4 cm joint depth. Bedding volume = 20 x 0.025 = 0.5 m³. Joint volume = (20 x 0.04) x 0.04 = 0.032 m³. Total = 0.532 m³, or 0.585 m³ (about 0.77 cubic yards) with a 10% waste allowance. Weight = 0.585 x 1,600 ≈ 936 kg (0.94 tonnes) -- about 38 bags at 25 kg each.
Pro Tips
Worked cost example: for the 0.585 m³ (about 0.94 tonnes with a 10% waste allowance) patio example above, at a typical Gibraltar price of around £58 per tonne, that's roughly 0.94 x £58 ≈ £54 in material cost, before delivery.
- Bedding sand and jointing sand aren't interchangeable. Sharp/bedding sand is coarser and meant to be screeded flat and compacted under the pavers; polymeric jointing sand is finer, with a polymer binder that hardens once watered in, locking the joints against washout and weed growth -- worth the extra cost anywhere vehicles will drive over the joints.
- Compact the bedding layer before laying pavers, not after -- screeding it flat and firm first stops the pavers settling unevenly once foot or vehicle traffic starts.