Concrete Column Calculator

UK concrete column calculator: work out concrete volume for round or square columns from diameter/side and height, with bag count and material cost.

Concrete Column Calculator: How Much Concrete for a Post or Pier?

Round posts, square piers, deck footings and fence columns all come down to the same question: how much concrete do you need to pour them? This calculator works out the volume of a circular or square/rectangular column from its diameter (or side length) and height, multiplies that by however many identical columns you are pouring, adds a waste allowance, and converts the result into either a bag count or a cement:sand:aggregate mix -- plus a material cost estimate.

How to Use the Concrete Column Calculator

  1. Choose the column shape: circular (diameter) or square/rectangular (side length).
  2. Enter the diameter or side length and the column height, in whichever unit suits you.
  3. Set the number of identical columns you are pouring.
  4. Adjust the waste allowance if needed -- 5-10% is standard.
  5. Pick bags or a custom cement:sand:aggregate mix, then read off the volume, bag count (or mix split) and estimated cost.

The Math Behind the Calculation

A circular column's volume is pi x radius² x height (the cylinder formula); a square or rectangular column is simply side x side x height. That per-column volume is multiplied by the number of columns, then inflated by the waste percentage to get the volume you should actually order.

Worked example: four circular posts, each 0.3 m (30 cm) in diameter and 3 m tall. Volume per post = pi x 0.15² x 3 ≈ 0.212 m³; for 4 posts that is about 0.85 m³ raw. Adding a 7.5% waste allowance gives roughly 0.91 m³ to order -- about 54 bags at a 0.017 m³ yield per bag (a typical 25 kg bag).

Pro Tips

At a typical material cost of around £125 per m³ of ready-mix concrete, four 0.3 m diameter, 3 m tall posts (about 0.91 m³ including 7.5% waste) cost roughly £114 in raw material -- formwork, reinforcement and labour are additional.

  • Leave at least 40-50 mm of concrete cover around a rebar cage on every side so reinforcement is not exposed at the surface.
  • Concrete columns cure on the same timeline as any other pour -- about 7 days to reach useful strength and around 28 days before full loading -- so avoid backfilling or loading a post footing early.